Structural steel frame design for the internal support arrangement of the primary boiler and fuel feed to new Energy From Waste facility in Lincoln.
Project Overview
Structural steel frame design for the internal support arrangement of the primary boiler and fuel feed to new Energy From Waste facility in Lincoln.
Client
CNIM
Contractor
Severfield
Location
Lincoln
Fabricator
Severfield
Project Description
Structural steel frame design for the internal support arrangement of the primary boiler and fuel feed to new Energy From Waste facility in Lincoln.
Project Challenges
The steel frame comprised a 40m gantry structure with multi level access and highly precise structure design tolerances to accommodate the energy plant. MP collaborated with the primary design team to confirm the structure design of the support, co-ordinating with the 3d modelling of the M&E installation.